Flooring scope of work
Rooms or areas: Rooms in this scope
Demolition
Remove the existing floor this scope replaces, and name the rooms.
Remove and put back the baseboards, or say they stay.
Framing
Repair soft or uneven subfloor, and how that extra work is written up before it is built.
Electrical
No new circuits, or a floor outlet or floor heat this scope includes.
Plumbing
Toilets or other fixtures that come off and go back on so the floor can be installed.
Fixtures
Transition pieces where the new floor meets a floor that stays.
Finishes
The flooring material, and who buys it.
Underlayment, and any moisture step the product calls for.
Permits and inspections
Who applies if your building department requires a permit, who pays the fee, and where the permit number is written before work starts.
Which inspections, if the department requires any, have to happen before the work is covered up.
Cleanup
Daily cleanup of the work area.
Haul-away of debris, and where a dumpster or trailer may sit.
How the work area is left at the end, including dust and leftover materials.
Who buys materials
A list of what you buy and what the contractor buys.
Who receives, stores, and installs items you supply, and what happens if one arrives damaged.
Allowances
Each allowance names the item, the quantity, and a dollar amount.
How a selection over or under the allowance is priced, in writing, before the item is ordered.
Schedule and milestones
A start date and a completion date for this scope.
The milestones that have to finish before the next part of the work starts.
Payment tie-ins
Which payment is tied to which milestone.
The final payment is tied to a completed punch list.
Warranty
Any labor warranty in writing: what it covers and for how long.
Who keeps the manufacturer warranties for materials the contractor supplies.
Exclusions
Repair of hidden damage found after demolition is not included until you and the contractor agree in writing.
Work outside the rooms or areas named in this scope is not included.
This is a draft you can send so contractors price the same work. It is not a contract and not a permit decision. Check with your local building department before work starts. For a dispute, talk with an attorney.