Deck scope of work
Rooms or areas: Deck
Demolition
Remove the existing deck, rails, and stairs, or say this is a new deck with nothing to remove.
Protect the siding, plants, and the path the crew will use.
Framing
Footings, posts, beams, joists, and the ledger, as the plan shows.
Rails, stairs, and guards this scope includes.
Electrical
Lighting or a new circuit, or a note that this scope has no electrical work.
Plumbing
No plumbing, or the hose bib or drain this scope moves.
Fixtures
Lights, hardware, and any built-in seating this scope includes.
Finishes
Deck boards or other walking surface, and stain or another finish if one is included.
Permits and inspections
Who applies if your building department requires a permit, who pays the fee, and where the permit number is written before work starts.
Which inspections, if the department requires any, have to happen before the work is covered up.
Cleanup
Daily cleanup of the work area.
Haul-away of debris, and where a dumpster or trailer may sit.
How the work area is left at the end, including dust and leftover materials.
Who buys materials
A list of what you buy and what the contractor buys.
Who receives, stores, and installs items you supply, and what happens if one arrives damaged.
Allowances
Each allowance names the item, the quantity, and a dollar amount.
How a selection over or under the allowance is priced, in writing, before the item is ordered.
Schedule and milestones
A start date and a completion date for this scope.
The milestones that have to finish before the next part of the work starts.
Payment tie-ins
Which payment is tied to which milestone.
The final payment is tied to a completed punch list.
Warranty
Any labor warranty in writing: what it covers and for how long.
Who keeps the manufacturer warranties for materials the contractor supplies.
Exclusions
Repair of hidden damage found after demolition is not included until you and the contractor agree in writing.
Work outside the rooms or areas named in this scope is not included.
This is a draft you can send so contractors price the same work. It is not a contract and not a permit decision. Check with your local building department before work starts. For a dispute, talk with an attorney.