A stop-work order is a written order from the building department to halt work. It is not a suggestion from the contractor and not a delay you can ignore because the tile is on site. The notice controls. Read it, photograph it, and ask the building department what restarts the job. One common reason is work that started without a permit. That path is in your contractor didn't pull a permit. Cities also stop work for other reasons. The paper on your door is the one that matters.
Why it often names you
On the city pages below, the order and the penalties are aimed at the owner. Your city will not copy these numbers. Two examples of what happens when work proceeds without a permit:
- Seattle. The city says it may issue a stop-work order against you if you start a building, addition, or remodeling project without a permit. If you build without a permit or do not get a final inspection approval, it may fine you or take other action, and the fine can be up to $500 a day (Seattle SDCI).
- Chicago. The city says it issues a stop-work order, and work can resume only after you get the permit and pay a stop-work penalty of $1,000 or more. In most cases the permit fee after a stop-work order is tripled. You have to correct violations and may have to remove work that cannot be corrected, at your own expense (City of Chicago).
Who was supposed to pull the permit is a contract question. The FTC lists "asks you to get any required building permits" as a scam warning (FTC). It does not move the city's order off your house.
Keep the notice next to the payment schedule. One room is free.
Start a free planTrack the next payment against the order
Keep the notice next to the payment schedule. One room is free.
Start your free projectWhat to read on the notice
- Who it names, and which address.
- Which work must stop. Some orders stop the whole site. Some stop one trade. Do not guess.
- What has to happen before work starts again, including a permit, a correction, or an inspection.
- Any date or fine printed on that sheet. Photograph the order and the work area that day. Write who you told, and when.
Call the building department yourself. Ask what they need to see. Do not let the crew "just finish this wall" on the stopped work. If the order is because nobody pulled a permit, the checks to make before the next job are in what to confirm about a remodel permit.
What to do about the next payment
Do not pay for the stopped work to keep going. Write the contractor: what stopped, the date, and that the next payment waits on a written plan to lift the order. A signed change order is the clean place for a new date and any cost to correct the work. See change orders.
If the contractor argues the order is your problem to ignore, slow down and follow what to do in a contractor dispute. The final payment still waits on the finish line in the contract, including a passed final inspection when the job needed one. See final payment and the punch list.
Keep the order with the permit file
The notice, the photos, the emails, and the inspection dates belong in one place. RenoBinder keeps the payment schedule and the change orders with the project. One room is free.
One room is free, with budget and change orders. A Project Pass ($49, 12 months) covers every room and adds CSV and PDF exports. See pricing.
Start a free plan and tie the next payment to the order →This is general information, not legal advice. Rules vary by state; for a dispute, talk to a licensed attorney or your state contractor board.
Track the next payment against the order
Keep the notice next to the payment schedule. One room is free.
Start your free projectLaunch offer: 30% off with code LAUNCH30