Whole-home remodel and addition checklist
This is general planning, not legal or code advice. Permit rules vary. Check with your local building department before work starts.
Updated 2026-11-19
A whole-home remodel or an addition is several projects that have to share one sequence. The kitchen, the bath, the roof, and a new room can each have a checklist of their own. This page is the order around them: where you will live, what gets designed first, and how the paperwork stays one file.
An addition is new structure. Treat the permit as a question for your building department before the design is finished. Check with your local building department. This page does not say what your lot allows.
Do I need a permit? · Check whether this project usually needs a permit. The checker is general. Check with your city.
Planning
- List every room that changes, and whether you are remodeling existing space, adding on, or both.
- Write the order you can live through: where you will sleep, cook, and bathe during each phase.
- Decide what has to be designed before anything is demolished. An addition's footprint and a kitchen layout both block other work.
- Confirm an addition sits on your lot. If you are not sure of the line or the easements, find that out before design treats the addition as settled.
- Pick the decisions that other rooms depend on, and order the long-lead items those decisions require before you open walls.
- If the house was built before 1978, ask about lead-safe work before old finishes are disturbed in any of the rooms. That question is separate from the building permit.
Budget and quotes
- Write one scope for the whole sequence, even if separate trades will price pieces of it. A kitchen bid that spends the whole budget leaves the bath unpriced.
- Ask each contractor to price their piece against that same scope, with exclusions written down.
- Ask who coordinates the trades if you do not hire one general contractor. Someone has to own the order.
- Keep money in the plan for work you cannot see yet, in every room you intend to open.
- Ask how a change in one room moves the schedule and the price of the next room.
- Compare proposals on the same room list. A lower price that drops the addition or the bath is not the same project.
Permits
- Take the room list, and the addition if there is one, to your local building department before you finish design.
- Ask what they need to see for an addition versus a remodel of existing rooms. Those are often different applications. Ask. Do not guess.
- Ask which inspections have to happen before finishes close each phase, so the schedule does not tile over work the department still needs to see.
- Write into the contract who applies, who pays the fees, and where you can see each permit number.
- Check with your local building department. An addition is new structure. A whole-home remodel may be several permit questions, not one.
During the work
- Keep one log for the job: who was on site, what changed, and which room is open.
- Photograph each phase before it is covered. Label the photos by room.
- Do not start the next room's finish while the previous room's inspection, if one was required, is still open.
- Write every change before it is built, including a change that only adds days.
- Protect the rooms you are living in. Say which doors and paths are the construction route.
- If a surprise shows up in a wall, stop that part of the work until the change is written down.
Final walkthrough and records to keep
- Walk every room on the original list, not only the room that finished last.
- Write one punch list for the whole job and tie the last payment to that list.
- Collect warranties, manuals, paint colors, and model numbers by room.
- Keep each permit number and inspection result with the contract for that phase.
- Save receipts beside the room they paid for, so a later question about the work has a file.
- When the punch list is done, keep the file. A whole-home project is hard to reconstruct from a camera roll.
Save the checklist with the job
Keep this checklist, your quotes, permits and receipts in one RenoBinder project — free
Start your free projectCommon questions
- What should I do before a whole-home remodel?
- List the rooms, the order you can live in the house, and whether you are also adding on. Write one scope, ask for quotes against it, and take an addition to your building department before design treats it as settled.
- Does a home addition need a permit?
- Ask your local building department before design is finished. An addition is new structure, and that is the kind of work departments review. What they need to see, and what the lot allows, is their answer, not a rule from this page.
- How do I keep records for a whole-home remodel?
- One file for the scope, the quotes, the contracts, change orders, receipts, photos by room, warranties, and each permit number. Split it by room so a later question does not depend on memory.