A remodel budget is really three numbers:
- Planned: what you meant to spend on each item
- Committed: what you've agreed to pay (a signed contract, an ordered product, an approved change order)
- Paid: what has actually left your account
Most people only track #3, and that's why overruns show up late. By the time the money has left, the decision that caused the overrun was made weeks earlier. Tracking committed against planned shows you the drift when you can still do something about it.
A simple tracking setup
For each line item, like cabinets, countertops, or tile:
| Item | Planned | Committed | Paid | Notes |
|---|---|---|---|---|
| Cabinets | Vendor, order #, lead time |
Add a separate list of change orders showing amount, days, and status. Then check two totals each week:
- Revised planned = planned + approved change orders
- Drift = revised planned − original planned
If drift is about to use up your contingency, cut something now rather than at the final invoice.
Keep receipts for taxes, too
Save the decisions and the budget in one place. One room is free.
Start a free planKeeping good records pays off long after the job is done. According to the IRS:
- Improvements add to your home's basis. Improvements "add to the value of your home, prolong its useful life, or adapt it to new uses," and you add their cost to the basis of your property (IRS Publication 523).
- Routine repairs usually don't count. Painting, fixing leaks, filling holes or cracks, and replacing broken hardware generally can't be added. But "the entire job is considered an improvement if items that would otherwise be considered repairs are done as part of an extensive remodeling or restoration of your home" (IRS Publication 523).
- How long to keep records: in general, until 3 years after the due date of your tax return for the year you sell the home (IRS Publication 523).
That can mean keeping kitchen receipts for decades. A shoebox won't last that long. A folder of photos is hard to search.
This is general information, not tax advice. Talk to a tax professional about your situation.
What to keep for each purchase
- The contract and every signed change order
- Invoices and receipts showing the amount, date, and what was bought
- Proof of payment (card statement, canceled check)
- Permits and final inspection sign-offs
- Product details for later: brand, model, color or finish code, and warranty terms
The last item isn't about taxes. It's what you'll need when a hinge breaks, a tile cracks, or you're trying to match the paint in five years.
Where RenoBinder fits
RenoBinder tracks planned, committed, and paid for every budget line, logs change orders with their status, and shows your drift on one screen. That's all free for one room. When the project wraps up, the free Home Finishes Record keeps the brands, models, paint codes, and warranties for every room.